2017-2022 Bond Project: District 3 Pedestrian Mobility & Streets
2017-2022 Bond Project: District 3 Pedestrian Mobility & Streets
The Bond Project will construct pedestrian mobility and street improvement projects.
Project Type: Streets, Bridges & Sidewalks
Phase: Construction
Project Contact: John Harris, 210-973-1694
Estimated Construction Timeline: Fall 2018-Winter 2024
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Associated Projects:
- McKinley Ave (S. Walters to Clark) – Construction to begin Summer 2024.
Project Budget: |
| ||
2017 General Obligation Bond (Street) | $9,000,000.00 | ||
Copper Point Contribution | $109,491.75 | ||
San Antonio Water System | $250,000.00 |
Total | $9,359,491.75 |
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Monica Cantu, 210-207-3935
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.