Cesar Chavez Avenue (Hall to Beacon)

Construction is expected to start early in late March/early April depending on the weather.

This is a reconstruction project. Contractors will replace the road and upgrade what is listed below:

  • Driveway approaches and sidewalks

  • Water

  • Parkways and street trees

  • Storm sewer

  • Streetlight poles 

Check out our Road Construction Guide to learn more.

Project Limits and Detour

The detour will use Hall, Sheridan, Century, and MLK Jr., shown in blue below. 

Cesar Chavez Avenue (Hall to Beacon)

Construction is expected to start March 30th

This is week 03-30-26 thru 04-03-26

  • Traffic device setup

  • manhole lowering

  • Milling roadway

  • Concrete removals 

Check out our Road Construction Guide to learn more.

Have a question?

Contact Us 

communityengagement@grcity.us

311 or 616-456-3000

Timeline

complete
complete
Wednesday, February 18: Construction Preparation Meeting

At this meeting we will share the work to be completed, project schedule, and access during construction.

 

planned
planned
Late March/Early April 2026 Construction Begins

The detour uses MLK Jr, Sheridan, Century, and Hall. 

 

planned
planned
End of August 2026: Construction ends

Construction is expected to end in August 2026.