Construction Updates:

  • September 2025 Update: The contractor will begin working near S. Tryon Street, McDowell Farms Drive, and Center Park Drive in September. 
  • August 2025 Update: The contractor is currently working in the area of Tyvola Road and Harry L. Jones Golf Course. 
  • March 2025 Update: The design for the greenway trail is complete, and the project has been bid. Construction began in May 2025 and should be complete in mid-2027. Check back for project updates regarding the construction schedule. 

You can download the greenway trail plan or the presentation slides from the public meeting in the Documents Section below. 

Greenway Trail Plan

Trailhead/Parking Lot Plan

You can also download a pdf of these plans below. 

July 12, 2023 Virtual Public Meeting

Question title

How do you plan to use Sugar Creek Greenway?

Click to view results

Question title

How would you like to access Sugar Creek Greenway?

Click to view results

Question title

Do you have any additional comments or questions about this project?

Project Schedule: 

complete
complete
Design + Permitting

complete
complete
Public Meeting

July 2023

complete
complete
Bidding

February 2025

live
live
Construction Start

Construction Start: May 2025

Anticipated Construction Duration: 2 Years

Greenway Master Plan:

Map of the Mecklenburg County Greenway Master Plan