PROJECT UPDATES

 

February 2026 - Project Update

Park and Recreation Staff, Design Consultant and Contractor participate in punch walk to inspect Archdale Park for documentation of outstanding construction related tasks.

Substantial completion is anticipated for April 2026 with project completion to follow soon after. 

 

 

December 2025 - Project Update

Misting ground, play structures and artificial turf have been installed. Fine grading, ground stabilization and plant install are still in progress.

 

 

November 2025 - Project Update

Fine grading, stabilization and sport court work continues.

 

 

October 2025 - Project Update

The Park continues to take shape...

 

September 2025 - Project Update

The Park continues to take shape with efforts focused on grading/compaction, shelter completion, concrete forming and court surfacing.

 

 

August 2025 - Project Update

Grading/Compaction and shelter work continues.

 

 

July 2025 - Project Update

Concrete work is powering forward during this stretch of dry weather and foundation work begins on shelters.

 

 

June 2025 - Project Update

Construction efforts related to grading/compaction for site amenities continues along with concrete forming in the proposed parking lot.

 

 

May 2025 - Project Update

Stormwater infrastructure and rough grading efforts continue.

 

 

March 2025 - Project Update

Erosion and stormwater control measures are installed and rough grading commences. Tree removal within limits of disturbance continues.

 

 

February 2025 - Project Update

Archdale Park is closed, due to active construction. Project completion is anticipated for Mid-2026.

 

 

Early 2025 - Pre-Construction Meeting

 

 

Fall 2024 - Non-Mandatory Pre-Bid Meeting