October 23, 2024 Update: Thanks to all of the Shadowlake neighbors who helped clear the streets from on-street parking for the bridge delivery on Tuesday, 10/22/24!


November 17, 2023 Update: Mecklenburg County is under construction on the 1.1 mile McAlpine Creek Greenway Trail segment between the existing trail and parking lot at Johnston Road and Pineville-Matthews Road (NC-51).  This project includes a new parking lot at Pineville-Matthews Road and connections to Ryder Ave, Pineville-Matthews Road/NC-51, and Johnston Road. The contractor is Eaglewood, Inc. and project is anticipated to be complete in Mid-2025. We look forward to seeing you on the trail in 2025.  


August 10, 2021 Update: Mecklenburg County Park and Recreation is providing an update on the McAlpine Creek Greenway project (Johnston Road to Green Rea Road). Due to difficulty acquiring the necessary real estate to make a greenway trail connection to Green Rea Road at this time, the Department is exploring a new trail alignment that terminates the greenway north of Highway 51/Pineville-Matthews Road (at the proposed trailhead parking lot). This alignment will include an access to Ryder Avenue, consistent with one of the options shared at the December 2020 virtual community engagement meeting (see map below). We will use any remaining project funding that would have paid for the connection to Green Rea Road to improve access to the greenway trail.  

The Bannington Road Connection Bid Alternate was not accepted as the cost exceeded the project budget. This access trail will need to be constructed in the future.

 

Question title

How do you plan to use this section of McAlpine Creek Greenway?

Click to view results

Question title

How will you most likely access this section of McAlpine Creek Greenway?

Select a response

Question title

Do you have any additional comments about this project?

Question title

* Would you like to provide your contact information for future project updates?

Project Schedule: 

complete
complete
Planning, Design, and Real Estate

complete
complete
Public Meeting

Virtual Community Meeting:

December 14, 2020 at 6:00 pm

live
live
Construction

Start: November 2023

Anticipated Completion: Late Summer 2025

Greenway Master Plan:

Additional questions? Contact: