PROJECT UPDATES

 
Fall 2025 - Project Status

Greenway construction continues with grading/compaction, base course install, and paving efforts associated with on grade trails. Bridge and boardwalk structures are being finalized with installation of complementary safety measures. 

**Note: Discovery of rock during excavation for a low water crossing dictated the necessity for rock hammering and removal. Loud noises are a byproduct and will be consistent until sufficient rock is removed. Hammering is anticipated to end no later than Friday, 9/19.

 

 

Summer 2025 - Project Status

Bridge structure at Hoover Creek has been set. Construction ongoing on with boardwalk installation, bridge rehabilitation and stormwater improvements.

 

 

Spring 2025 - Project Status

Active construction for the Walker Branch greenway segment has commenced. Bridge work is ongoing at the Hoover Creek segment.

 

 

Early 2025 - Project Status

Construction is ongoing at the Hoover Creek greenway segment with continuation of bridge related activities. 

 

 

Fall/Winter 2024 - Project Status

Greenway construction is ongoing with concentrated efforts along the Hoover Creek segment of the project. Active construction for the Walker Branch segment, beyond initial clearing and grubbing, to start by Early 2025.

 

 

Spring 2024 - Pre-Construction Meeting

 

 

Fall 2023 - Non-Mandatory Pre-Bid Meeting

 

 

Summer 2020 -  Preliminary Alignment Assessment